進捗 is read shinchoku. It refers to progress in work or another undertaking and appears frequently in Japanese business communication. A useful update goes beyond the word itself: explain what is complete, what remains, and when the information was checked.
Read 進捗 as shinchoku and understand its basic meaning
The Japanese dictionary Kanjipedia gives the reading shinchoku and a meaning related to work advancing. Common phrases include 進捗を確認する, “check progress,” and 進捗をご報告します, “report on progress.” See the Kanjipedia entry for 進捗.
The basic word does not require a percentage or a comparison against a plan. You can say that an investigation has made progress without expressing it numerically. In a workplace update, naming the deliverable and status time helps the recipient understand what has advanced.
When someone asks 進捗はどうですか, “How is progress?”, add a verified fact rather than replying only “It is going well.” For example, “The outline is approved and the body text is being drafted” distinguishes an accepted result from work in progress.
Distinguish shinchoku from related Japanese terms
Several Japanese terms overlap with shinchoku. The table gives useful tendencies, not rigid categories that never overlap. The natural choice depends on the sentence and the information you want to emphasize.
Japanese term | Typical emphasis | Example and meaning |
|---|---|---|
進捗 — shinchoku | How far work has advanced | 制作の進捗を共有する — share production progress |
進行 — shinkō | The process or conduct of something | 会議の進行を担当する — facilitate a meeting |
進展 — shinten | A development that moves a situation forward | 交渉に進展があった — negotiations made headway |
経過 — keika | The course of events over time | 復旧までの経過を説明する — explain events up to recovery |
状況 — jōkyō | The current state or circumstances | 承認待ちの状況を確認する — check the state of pending approval |
進捗状況 is common in business use. 進捗が進む can sound repetitive because both parts convey advancing; 作業が進んだ or 進捗があった may read more naturally. More important than correcting a label is making the object and facts clear.
Use natural phrases in conversations and email
In conversation, 制作の進捗を共有してもらえますか asks someone to share production progress. In email, 本日15:00時点の進捗をご報告します introduces an update as of 15:00 today. Adjust formality to the recipient while retaining the object and status time.
- Request: “For the material due D5, could you explain what has been checked and what remains?”
- Report: “As of D3 at 15:00, the outline is approved and drafts of three of five chapters have been shared.”
- Forecast: “If the copy is finalized today, we expect to move to final review on D4.”
- Unknown: “The approval time is unconfirmed. We will check with C and update at 16:00.”
A shared draft is not necessarily an approved chapter. Use drafted, submitted, and approved according to what has actually been verified. If people interpret completion differently, agree on the state definitions before comparing percentages.
A brief conversation or email can both work. In urgent situations, explain the decision the information supports so the recipient knows which clarification matters.
State the basis, completion rule, and date of a percentage
When reporting a percentage, include its denominator, completion rule, and status time. This fictional example concerns ten deliverables of the same specification and with the same acceptance conditions. Compare actual and planned completion using the same counting rule and point in time.
Measure | Calculation | What it indicates | What it does not establish |
|---|---|---|---|
Six deliverables approved | 6 ÷ 10 × 100 = 60% | Share of the defined deliverable count complete | That 40% of the effort remains |
Plan at the same time: eight approved | 8 ÷ 10 × 100 = 80% | Actual is two items, or 20 percentage points, below plan | A delay of the same proportion |
20 person-hours used against an initial 40 | 20 ÷ 40 × 100 = 50% | Effort consumption relative to the original estimate | That half the deliverables are complete |
Five of ten planned working days elapsed | 5 ÷ 10 × 100 = 50% | Elapsed share of planned duration | That completion is 50% |
The difference between 60% and 80% is 20 percentage points, not a relative reduction of 20%. If deliverables differ substantially in size, a simple item count may be inadequate; explain the remaining work as well.
Microsoft Project’s official field guidance distinguishes work-based and duration-based percentages. Check what the measure represents rather than automatically treating it as accepted-output completion. Read Microsoft’s percent-work-complete field guidance.
Report facts, the plan gap, and the forecast concisely
A concise status update combines facts, the plan gap, remaining-work forecasts, and support required. The following is a separate fictional example involving five banners, not the ten items above. All times are JST; D3 and similar labels refer to agreed dates.
Update field | Worked entry |
|---|---|
Status time | D3, 15:00 JST |
Facts | Three of five banners have passed mandatory-text and size checks and approval; two are being revised |
Plan gap | Five approvals were planned by this point; two remain unapproved |
Remaining work and forecast | Revisions submitted D4 at 10:00; C reviews by 12:00; corrections and recheck forecast complete at 17:00 |
Downstream effect | The D5, 12:00 release decision remains feasible if those review and correction assumptions hold |
Support and next update | Arrange C’s review slot; update D4 at 12:30 |
A short version could read: “As of D3 at 15:00, three banners are approved and two are being revised. If C reviews by D4 at 12:00 and corrections stay within the estimate, we forecast completion at 17:00. The effect on the D5, 12:00 release decision depends on those assumptions. Please help arrange C’s review slot.”
Before saying there is no downstream effect, verify the successor’s start conditions and required margin. Having only two items left does not prove the deadline is safe. If an assumption changes, update both the completion forecast and the downstream decision.
Identify unknowns and the next update
Separate unknowns from established facts. “Checking” alone does not tell the recipient whether to wait or act. Identify the person who will confirm the information, the answer needed, and the next update time.
For example: “C’s review availability is unconfirmed. Coordinator B will check by 16:00 today. If no slot is available, we will reassess remaining work and the release-decision timing.” Do not present a forecast that depends on an unresolved condition as a confirmed delivery commitment.
- Identify the object and status time.
- Describe completed and remaining work on the same basis.
- State the plan gap and assumptions behind downstream effects.
- Assign confirmation of unknowns and the next update.
A progress update is useful when it supports the next check or decision. It does not need an impressive-looking percentage; it needs an understandable account of the current state.
Related reading
- How to Ask for a Progress Update: Email and Reply Examples Before and After a Deadline
- Weekly Campaign Progress Template: Filled Examples and Review Rules
- What Is a Gantt Chart? A Worked Guide to Bars, Dependencies, and Schedule Delays
References (checked October 10, 2026)